-Testing+===== Deployment of new Features ===== 
 + 
 +On this page we describe the procedure for deploying new features on the web application. 
 + 
 +1. The developers have until Fridays 10:00 AM to prepare the new features that will be deployed on production. The preparation comprises the following steps. 
 +  * Test the implementation. 
 +  * Push it to the central repository. 
 +  * Update the [[FeatureArrivals]] list. 
 +       * Provide the deployment instructions. 
 +       * Mark its status as Landing. 
 + 
 +2. Every Friday, between 10:00 AM and 11:00 AM, all Landing features are deployed on the production environment. The administrator takes the following steps. 
 +  * Collect all new features pushed to the central repository during the past week. 
 +  * Deploy them on production, following the instructions provided by the developers. 
 +  * Update the [[FeatureArrivals]] list. 
 +      * Mark its status as Grounded. 
 +      * Inform the same target release for all device features deployed on that day. 
deploymentprocedure.1279896949.txt.gz · Last modified: 2012/10/30 10:35 (external edit)